China labeling machine manufacturer, OEM/ODM, semi-automatic to high-speed rotary systems.

Labeling Machine Manufacturer Guides

Uptime Clause: Which Stops Count Against the Supplier?

An uptime clause is a formula with four decisions written into the purchase contract, and month one is where those decisions meet an installed machine. The four decisions are the two clocks, the closed list of exclusions, the boundary between supplier stops and buyer stops, and the evidence attached to every stop.

On a pressure-sensitive labeler the stops deciding the argument are rarely breakdowns. Changeover and format trials, starvation from the filler and blocking from the case packer consume more contested time than mechanical failure on most bottling lines, and each of the three needs a bounded definition before day 1.

One rule settles most disputes: an undocumented or disputed stop stays charged to the supplier until the supplier proves the exclusion. What follows is the clause chain from that rule to a first-month ledger, and the test deciding whether the ledger proved anything. With the ledger, the alarm history and the acceptance record on the table, the figure stops being an opinion.

Step 1: Why Is an Uptime Percentage Not a Clause?

An uptime percentage is a ratio whose denominator stays undefined until the contract names scheduled production time, so a figure alone settles nothing. According to the trade-press analysis of equipment purchase agreements, an uptime guarantee sets forth a formula comparing actual operating time to scheduled operating time, which already contains four decisions before any number is written.

First, what counts as scheduled time: calendar hours, paid shifts, or hours with a crew and a product to run. Second, what counts as running: shaft rotation, or conforming output at the ordered rate. Third, which stops leave the numerator. Fourth, who decides a disputed stop, on what evidence, and by which deadline.

For example, a line running three shifts with two format changes per shift reports a different figure from the same machine on one long run. The clause must name the line being measured.

Step 2: Which Two Clocks Does the Ratio Need?

Two clocks define an availability clause: a scheduled production clock taken from the shift calendar the plant really runs, and a downtime clock counting only stops the machine owns. The second clock is the negotiation, because every exclusion moves time out of the numerator.

First, scheduled production time is the calendar minus planned shutdowns named in the contract. Nameplate hours have no place in the denominator, since a machine cannot be unavailable during a week the plant is closed.

Second, the exclusion list is closed rather than illustrative. Scheduled maintenance with notice, force majeure, operator error, facility utilities, and upstream or downstream stoppages may sit on the list, and each one needs an owner, a notice deadline and the evidence claimed.

Finally, anything absent from the list stays charged, so a category nobody discussed at signature does not become the supplier’s argument in week four. Installation days are a different clock, and offline pre-build and installation downtime belong outside the denominator.

Step 3: Which Three Labeler Stops Get Misclassified?

A labeler stop is changeover when the line stands between products, and the changeover category needs a clock of its own, otherwise the supplier’s figure is decided by the customer’s SKU count.

First, changeover and format trials cover roll changes, change parts, recipe selection and a first run on a new bottle. Bound the category by the number of formats the contract names and by a time budget per format, so a trial beyond the contracted mix stays with the buyer.

Second, starvation means the labeler is empty because the filler ran dry. Excuse the stop only with the upstream record named in the exclusion, such as the filler stop log for the same minute.

Third, blocking means the case packer or the discharge conveyor is full, and the same evidence rule applies downstream. Three named categories absorb most of the argument on a bottling line, and one unnamed category absorbs the rest.

Step 4: When Does the Clock Start and Stop?

The clock starts when the machine stops or cannot make conforming product, and stops only after a documented restart and a production check, not when a technician calls the repair complete. A repair closing at 14:00 and a line delivering conforming bottles at 15:20 are two end times, and the clause must name the second.

Disputed or undocumented time stays charged until the supplier proves the exclusion, and the burden of proof belongs in writing beside the notice deadline. A missed target nobody reported inside the window is a missed claim.

Evidence at each end of one event: the fault code with a timestamp at the start, the first conforming output with a timestamp at the end, and the work order linking the pair. The handover pack and the technician test decide whether the crew can produce that evidence in week one.

Step 5: Which Codes Must Be Locked Before Day 1?

A locked code list is a fixed set of fault, alarm and idle states agreed by both sides before production starts, and the list is the only vocabulary the ledger accepts. A code list agreed after an event is a negotiation wearing a label.

First, take alarm and fault codes from the HMI and the PLC historian, and keep the numeric code exactly as the machine prints it. Second, keep idle states separate: starved, blocked, no operator, no label roll, no product. Third, place maintenance and trial categories beside the fault codes rather than inside them.

Name the owner of each data source: historian export, alarm log, work orders, production record. A ledger drawing on one source cannot survive a disagreement, and a crew holding the HMI export at day 31 can still answer a question asked in month three.

A hot-melt glue labeling machine at a workstation, where the fault code and the stop time of each event are read from the HMI and written into one joint log

Step 6: What Does One Ledger Row Have to Contain?

A ledger row is the smallest unit of evidence in an availability claim, and a row without a code, a timestamp pair and two signatures is a note rather than evidence.

One row carries eleven fields: event number, start time, stop time, machine state, alarm or fault code, product and ordered rate, people present, cause as determined, category, evidence attached, and two signatures, one from each side.

First, count every minute once, because two logs for one event double the charged hours. Second, attach the HMI export beside the row, so a reader at month three can reopen the fault without asking the shift. Third, keep the cause field empty until evidence closes the argument, since a guessed cause becomes a category.

For example, three rows from one shift tell a complete story: a starved stop excused with a filler record, a format trial inside the contracted budget, and a sensor fault with no evidence still charged to the supplier.

Step 7: What Makes the Test Prove the Number?

Which Population Does the Test Run On?

A first-month test is a measurement on a stated population, and the population covers the shift pattern, the product mix, the ordered rate and the defect allowance, all written before the window opens in 2026. Thirty calendar days are a period, not a population.

First, count conforming output at the ordered rate rather than shaft motion, with the band from 15 to 30 pcs/min on a semi-automatic unit and 40 to 300 pcs/min on a fully automatic unit named in the schedule.

Second, list the SKUs in the window, because a demonstration on easy bottles at half speed proves little. Third, put a witness from each side on the window and fix the export format in the schedule.

According to a factory and site acceptance comparison, a successful FAT does not automatically prove a system will work after transport, installation, wiring and integration with site equipment, so a FAT figure is not the first-month figure.

What Is the Remedy Ladder When the Window Fails?

A remedy ladder is a fixed sequence of consequences written before the result exists, because a remedy negotiated after a miss is a discount rather than a fix.

First, re-measure a second window on the same code list and the same population. Second, place the supplier on site for the failing category. Third, parts and support for the failing category at supplier cost. Fourth, a written corrective action with dates and a named owner. Fifth, and only after the four steps, the acceptance and warranty consequence.

In practice, a buyer names ISO 22400-1 for vocabulary and still writes the arithmetic in plain words, since a standard number settles nothing until the timetable and the code list exist. A measurable SAT clause follows the same shape: baseline first, then the number, then the witness.

Step 8: What Goes in the Clause Checklist and the Ledger?

Which Clause Produces Which Evidence?

Every clause in the schedule produces one artefact, and a clause producing no artefact is a sentiment. The checklist runs in four columns: the clause, what the clause must state, the evidence produced, and the signer.

First, the clock clause states the shift calendar and the closed exclusion list. Second, the code clause states the locked list and the data sources, signed by both sides before day 1. Third, the row clause states the eleven ledger fields and the two signatures. Fourth, the notice clause states the deadline and the recipient of a claim. Fifth, the remedy clause states the ladder and the dates.

Commercial terms stay as agreed: MOQ one unit, 30 percent deposit with 70 percent before shipment, FOB Shenzhen, and one year of warranty with lifetime support. The ledger does not reopen the payment split. The ledger is the attachment making the acceptance record and any later warranty claim readable, and the warranty claim evidence file is where a failed window eventually lands.

The Ledger Columns and the Clause Rows

Clause What the clause must state Evidence produced Signer
Two clocks Shift calendar, nameplate hours excluded, closed exclusion list with owner and notice deadline Calendar plus exclusion schedule at order Buyer operations and supplier
Locked code list Alarm and fault codes as the HMI prints them, idle states, trial category Code list version dated before day 1 Both sides, before production
Clock rule Start at stop or non-conforming output, end at the first conforming bottle Timestamp pair with the work order linking both ends Line engineer and supplier
Ledger row Eleven fields and two signatures for every event, one joint log only Joint log export with alarm history attached Buyer quality and supplier
Population Shift pattern, SKUs, ordered rate band, defect allowance for the window Window schedule with witness names Both sides, before day 1
Remedy ladder Second window, on-site support, corrective action dates and owner Corrective action record and re-measurement export Purchasing and plant manager

Frequently Asked Questions

Which Stop Counts Against the Supplier on a Labeler?

An unexcused stop counts against the supplier, and the exclusion list is closed: scheduled maintenance with notice, force majeure, operator error, facility utilities, plus starvation and blocking carrying the named upstream or downstream evidence. Anything else stays charged until the supplier proves the exclusion in writing, on the locked code list.

Is a Starved Labeler a Supplier Stop?

Starvation is the labeler waiting for bottles, and the excuse holds only with the upstream record named in the exclusion, such as the filler stop log for the same minute. Without that record the time stays charged, so review the evidence rule before the first window opens rather than after a claim.

Can a FAT Result Serve as the First-Month Figure?

No. A factory acceptance test is a pre-shipment check at the supplier’s facility, and a site acceptance test is a check on the installed machine with site utilities and interfaces. A first-month figure is measured on the buyer’s own line over 30 production days, on the locked code list and the joint ledger, at the ordered rate. In practice, the FAT record answers whether the machine was built to order.

Does the Ledger Change the 30/70 Payment Terms?

No. The payment structure stays as agreed, with a 30 percent deposit and 70 percent before shipment. The ledger is an evidence artefact, and the contract schedule carries it as an attachment, so the acceptance record, the second-window decision and any warranty claim rest on the same signed rows.

Get a factory quote for your own container.

Send the container, label size and target speed. You get a short list of machine options, an indicative price and a free test-run plan on your own labels.

Get a Factory Quote Request a Free Test-Run Video

Share

Related reading

Keep reading.

More guides from the same category, chosen for the machine types and container details they cover.

Labeling Machine Manufacturer Guides

Die-Cut Gap or Eye Mark: Whose Drift Is It?

Registration drift on a pressure-sensitive labeler reaches a distributor as an argument rather than as a fault, and the argument returns with every batch because three parties measure three different things. A die-cut gap and an eye mark are converter geometry. Registration is a machine reading of that geometry at line speed. Once the numbers ... <a title="Die-Cut Gap or Eye Mark: Whose Drift Is It?" class="read-more" href="https://hipaks.com/die-cut-gap-eye-mark-drift-order-lines/" aria-label="Read more about Die-Cut Gap or Eye Mark: Whose Drift Is It?">Read more</a>

Nov 26, 2026 · 11 min read
Read guide
Labeling Machine Manufacturer Guides

How Many Bottles Prove a Labeler? The Sampling Plan

An acceptance sampling plan for a labeler is a rule for deciding, from a counted sample of labelled bottles, whether the machine may be accepted, and the bottle count is the last item to fix rather than the first. Five parts carry the plan: the population, one bottle lot crossed with one label station and ... <a title="How Many Bottles Prove a Labeler? The Sampling Plan" class="read-more" href="https://hipaks.com/labeled-output-acceptance-sampling-defect-classes/" aria-label="Read more about How Many Bottles Prove a Labeler? The Sampling Plan">Read more</a>

Nov 25, 2026 · 11 min read
Read guide
Labeling Machine Manufacturer Guides

Metal Detector False Rejects: Whose Filter, Whose Shield?

A metal detector false-reject on every drive ramp is three faults sharing one symptom, and the drawing able to separate the three is the interface drawing between the machines, not the labeler’s own electrical sheet. According to IEC 60204-1, the equipment covered begins at the point of connection of the supply and covers a group ... <a title="Metal Detector False Rejects: Whose Filter, Whose Shield?" class="read-more" href="https://hipaks.com/labeler-vfd-emi-metal-detector-checkweigher-interface/" aria-label="Read more about Metal Detector False Rejects: Whose Filter, Whose Shield?">Read more</a>

Nov 23, 2026 · 10 min read
Read guide

Not sure which machine fits your line?

Send the container and the target speed. HiPaks replies with machine options, an indicative price and a test-run plan on your own labels.

Get a Factory Quote Find Your Machine in 3 Steps
Back to top