A handover pack is the set of documents, cards and backups a distributor needs to support one labeling machine without calling the factory for every fault. One technician can carry the support alone on three conditions. Completeness is counted, not judged: one card per alarm code in the HMI table, one line per change part on the parts list. The test runs on a format the distributor will sell, and the first-off is signed against the placement specification rather than against the technician’s eye. The backup is restored once, in front of a witness, before the 70% balance is released under 30/70 TT. The pack also needs an owner, a revision trigger and a customer edition, because a pack starts to expire when the commissioning engineer leaves.
What Makes a First Handover Fail?
A first handover is a competence test with a countable pass mark, and the test fails in five ways. 1. One pack serves three readers with three different lifetimes. 2. The alarm cards cover the codes the manufacturer had on file, not the codes the installed software can display. 3. The test runs on the factory demonstration bottle instead of a format the distributor will sell. 4. The backup is filed and never restored. 5. The pack has no owner on day 31, so the first software update makes every card out of date. The five failures share one cause. The handover was run as a document transfer, and the distributor pays for the difference at the first customer call. Stocking decisions belong to the used-machine stocking tests, because the first handover starts after the order is placed.
Failure 1: One Pack for Three Readers
Who Reads the Pack, and for How Long?
A three-reader pack is a set of three documents with three lifetimes, not one manual split into chapters. The internal service pack stays with the distributor: full schematics, the PLC and HMI backups, the parameter list, the escalation template and the spare-part numbers. The service pack lives as long as the machine is supported, and every software change restarts the clock. The customer operator pack leaves the distributor: changeover steps, daily checks, operator-level alarm cards, cleaning notes and safety points. The customer pack lives until the product, label or language changes, and the customer’s own site file holds the master copy. The escalation pack travels back to the manufacturer: serial number, software revision, alarm text, photographs and the checks already made. For example, the escalation pack is rebuilt for each incident, so the template is permanent.
What Does the Document Register Hold?
A document register gives every deliverable a revision, an owner, a format and a status.
| Deliverable | Revision | Owner | Format | Status |
|---|---|---|---|---|
| Alarm card set | Rev 3 | Service lead | Laminated card and PDF | Approved |
| Changeover procedure | Rev 2 | Distributor technician | PDF and printed copy | Approved |
| PLC and HMI backup | As built | Manufacturer controls engineer | Project archive and USB | Restore verified |
| Change-part list | Rev 1 | Manufacturer spares desk | Spreadsheet and PDF | Approved |
| Customer operator pack | Rev 1 | Distributor, translated | PDF in customer language | Draft until checked |
| Handover certificate | As signed | Distributor and manufacturer | Signed at FAT |
Failure 2: The Alarm Card Covers the Wrong Alarms
How Do You Count Cards Against the HMI?
Countable completeness means 100% coverage of the alarm codes the installed HMI can display, and the count is a reconciliation rather than an opinion. The HMI alarm table at the tested software revision is the source, not the manufacturer’s master list, because a machine built for one market can hide codes another machine shows. First, count the codes in the HMI table. Second, count the cards in the pack. Third, write both totals on the certificate. The difference must be zero. The same method covers spares: one line for every item on the change-part list, and one line per part number, with the numbering method in the spare-parts stock list. According to HSE, employers must provide adequate, clear information and written instructions where necessary, and a pack missing a code is not adequate. For example, a card with the right code and the wrong reset order sends the technician back to the same fault.
When Must the Technician Call the Factory?
An escalation rule is a written list of conditions where the technician stops work and calls the manufacturer, and the rule sits on the card, not in a manual. Five conditions mark the calls to escalate. 1. The alarm code is not on the card. 2. The permitted checks are exhausted and the fault remains. 3. The fault touches a guard, an interlock, an emergency stop or a safety circuit. 4. The same fault returns after a reset in the same shift. 5. The repair needs a password above technician level or a parameter change in the PLC or HMI. The escalation pack carries the machine serial, the software revision, the exact alarm text, a photograph of the screen, the checks already made and the label lot. According to HSE, work equipment must be used only by people who have received adequate information, instruction and training, and the escalation rule is where training stops.
Failure 3: Why Does the Demo Bottle Pass?
A handover test is a measurement on the format the distributor will sell, and the factory demonstration bottle is the easiest format in the building. The first customer may run a soft PET bottle, a curved label panel, a small label or a liner the factory never saw. The test runs on the bottle, the label and the adhesive the distributor will sell, and the first-off is signed against the placement specification. According to HiPaks factory practice, the buyer’s own bottles are labeled before shipment and the video comes back with the machine, so the distributor can send the customer’s bottle and label instead of accepting a demonstration run. Placement is measured, not watched: ±0.5 mm on a semi-automatic machine, ±1 mm on an automatic machine and up to ±0.2 mm on the MT-807, excluding product and label variation. Three consecutive bottles inside the band close the test, and the first three failures are answered by one test matrix.

The Test Matrix: What Proves the Pack Before the Balance?
Which Test Proves Which Deliverable?
The test matrix maps each deliverable to the test that proves it, the handover gate where the test closes, the evidence kept and the signatures. Five gates carry the pack: design, FAT, shipping, installation and SAT.
| Deliverable | Test that proves it | Gate | Evidence kept | Signatures |
|---|---|---|---|---|
| Changeover procedure | Cold start, no help, customer bottle and label, inside the agreed duration | FAT, repeated at installation | Timed sheet and first-off record | Technician and witness |
| Alarm card set | One fault injected by a safe reversible method, cleared from the card alone | FAT | Card number, steps taken, screen photograph | Witness |
| Escalation rule | A fault the card marks stop, and the technician files the form instead of resetting | FAT | Completed escalation form | Witness |
| Completeness | Cards against the HMI table, parts against the change-part list | Design and FAT | Two totals and a zero difference | Manufacturer and distributor |
| Backup | Restore from the archive, then a first-off | FAT, repeated after any update | Restore log and revision string | Technician |
| Customer edition | Operator task performed from the translated pack | SAT | Observed task and translation log | Distributor |
How Is the No-Help Test Witnessed and Recorded?
A no-help test is a witnessed run where the technician performs the task with the pack open and the supplier present but silent, and the pass is recorded as evidence rather than opinion. The run starts cold: machine isolated, tools on the bench, pack at the page. First, the technician performs the changeover on the customer’s bottle and label and reaches a first-off inside the agreed duration. Second, a fault is injected by a safe reversible method, for example a sensor blocked with a test card, and the technician clears the fault from the card alone. Third, the backup is restored and a second first-off confirms the machine. The witness records the time, the pages used, the questions asked and every failure point. A second run after a gap separates a competent technician from a lucky one. What consumes changeover time is set out in the changeover time and SKU count.
Failure 4: The Backup Exists and Was Never Restored
What Does a Restore Test Prove?
A restore test is a recorded rebuild of the machine’s control state from the archive, and a backup never restored is a file rather than a backup. The archive holds the PLC program, the HMI project, the recipe and parameter set, the drive parameters and the vision job where one exists, each tagged with the software revision on the machine. First, the archive is opened on a clean machine or a spare controller of the same model. Second, the revision string is compared with the as-built record. Finally, a first-off confirms placement. The record carries the archive name, the revisions before and after, the person who restored, the time taken and the first-off result. A restore needing the manufacturer’s laptop is not a distributor capability, so the pack names who holds the tool and licence.
Day 31: Who Owns the Pack After the Engineer Leaves?
Failure 5 is a pack with no owner, and day 31 is the first working day after commissioning support ends. The owner is a role at the distributor, usually the service lead, with authority to withdraw a card from a customer site. Six triggers force a new revision: an HMI or PLC software update, a superseded sensor or drive, a new format or label size, a new customer language, a changed guard or safety circuit, and an alarm code added or removed. Each trigger increments the revision, withdraws the old cards, updates the customer edition and re-signs the training record. According to HSE, training may need to be refreshed at suitable intervals, and changes in work equipment or the system of work may require additional training. A pack with no owner does not fail on day 31. The pack fails on the day of the first software update, when every card is quietly wrong.
Why Is the Customer Edition a Legal Duty?
A customer edition is the operator pack rewritten in the language the customer’s operators read, and the edition is a legal duty rather than a courtesy. In the United Kingdom, PUWER regulations 8 and 9 put the duty to provide adequate information, instruction and training on the employer who puts the equipment into use, and a pack an operator cannot read is not adequate information. The distributor who supplies the machine and trains the customer’s staff performs part of the duty, so the translated edition belongs in the handover. According to HSE, there is no bar to training being given by competent in-house staff, provided the staff can assess the skills attained, and the lift-truck code describes three stages: basic, specific job and familiarisation. Finally, the customer’s operator performs the changeover from the translated pack while the technician watches and scores.
What Does the Handover Certificate Release?
A handover certificate is a one-page record of what was tested, on which format and at which revision, and the certificate releases the balance rather than the machine alone. The page carries the serial, the software revision, the pack revision set, every procedure tested, the customer’s bottle and label reference, the first-off result, the deviations and the open points with an owner and a date. Two signatures close the page: the distributor’s technician and the manufacturer’s witness. The certificate does not certify competence in general, only one date, one format and the listed tasks performed without help. Under 30/70 TT the 70% balance is released before shipment, so the certificate is signed at the factory acceptance test and the installation test becomes a repeat.
Frequently Asked Questions
Can One Technician Support a Labeling Machine Alone?
The answer is a written scope, not a training certificate. The scope covers changeover, cleaning, the card alarms, the backup restore and the escalation decision. Anything outside the scope stops and escalates. The no-help test proves the scope on the customer’s format.
How Many Alarm Cards Should the Pack Contain?
The count is a reconciliation, not a fixed number. One card for every alarm code the installed HMI can display, taken from the alarm table at the tested software revision. The pack is complete when cards and codes match and the difference is zero.
What Should the First-Off Be Signed Against?
A first-off is a measured placement result, signed against the specification for the machine class: ±0.5 mm on a semi-automatic machine, ±1 mm on an automatic machine and up to ±0.2 mm on the MT-807. The measurement runs on the customer’s bottle and label, three bottles in a row.