A metal detector false-reject on every drive ramp is three faults sharing one symptom, and the drawing able to separate the three is the interface drawing between the machines, not the labeler’s own electrical sheet. According to IEC 60204-1, the equipment covered begins at the point of connection of the supply and covers a group of machines working together in a co-ordinated manner, which is a three-machine case. Inside the boundary, five measures belong on one drawing, each with one named owner and one piece of evidence. Outside the boundary no measure has an owner. This article sets out the five rows, the two shield rules and the commissioning record.
Why Does One False Reject Hide Three Different Faults?
Which Fault Is the Detector Reporting?
A false reject is a detector output at the reject line, and the output reports a disturbance at the search head rather than a cause. The table sorts four observations by the reading which separates one fault from another, the alternative eliminated by that reading, and the person able to sign. According to IEC 60204-1, the equipment covered begins at the supply connection, so a reading taken outside the boundary proves nothing about the line. In practice a retrofit spends longer on scope than on cable.
| Seen | Happening | Reading that separates | Rules out | Signer |
|---|---|---|---|---|
| Good bottles rejected on ramp | Signal-cable coupling from motor cable | Detector output, drive stopped then ramping | Product or aperture fault | Integrator |
| Test piece fails only on ramp | Sensitivity reduced during ramp | Test piece before and after each ramp | A tuning change | Detector owner |
| Checkweigher zero drifts | Load-cell cable in motor tray | Zero against calibrated test weight | Product weight variation | Checkweigher owner |
| Reject arm shakes on ramp | Loose bracket | Marker across the bracket joint | EMI entirely | Fitter |

Why Do the Three Machines Disagree About the Cause?
Each machine reports from inside its own boundary, and a report from one boundary cannot describe a cause inside another. The detector states a disturbance at the search head. The checkweigher states a change in weight against a stored reference. The labeler states a ramp in drive current. Three reports, three instruments, three owners, and no shared reading. The disagreement is structural rather than technical: the three machines were never asked to report the same event, and the PLC I/O list assigns signals rather than events. The first drawing task is therefore to define one event all three machines can describe: the ramp, with drive current as the trigger and counts as the outcome.
Where Does the Interface Drawing Start, and Which Standard Already Says So?
What Boundary Does IEC 60204-1 Draw?
The boundary belongs to the standard rather than to the drawing office. According to IEC 60204-1, the requirements apply to electrical equipment of machines not portable by hand while working, including a group of machines working together in a co-ordinated manner, and the equipment covered commences at the point of connection of the supply. The published summary of significant changes lists revised electromagnetic compatibility requirements, revised protective bonding requirements and terminology, and added requirements for applications involving power drive systems. 1) The supply connection is the left edge of the sheet. 2) A group of machines is one subject, so the three frames share a boundary. 3) Drives and bonding sit inside the scope rather than outside. Finally, the left edge, according to IEC 60204-1, is also where an unstable supply enters, and the supply specification stays a separate document with a separate signer.
Why Is the Generic EMC Standard Not the Line Test?
A generic standard is a fallback, and the fallback is written into its own scope. According to IEC 61000-6-2, the publication is the generic immunity standard for industrial environments, and the published abstract states that the generic standard applies if no relevant dedicated product or product-family EMC immunity standard exists. A line built from a labeler, a metal detector and a checkweigher is a line of three products, and each product may carry a dedicated standard of its own. Before the generic standard is named as an acceptance basis, the buyer has to establish whether a dedicated standard exists for each of the three machines. The product page publishes an abstract rather than a test procedure, so the switch-on record in the last section carries the acceptance instead.
Which Five Measures Go on the Drawing, and Who Signs Each One?
What Are the Five Rows?
Five measures cover the interface, and each row carries the same three fields: supply, install, verify. First, the VFD input filter, supplied with the drive and bonded to the mounting plate, verified by continuity from the filter housing to the plate. Second, a shielded motor cable terminated at both ends, verified by a gland clamp which carries the braid around the full circumference. Third, segregation of power and signal along the whole run, verified by a photographed tray layout rather than a remembered intention. Fourth, an equipotential bond between the three frames, verified by a reading at each named stud. Fifth, the victim side: a detector signal cable shielded and bonded at the detector end, with hardening agreed in writing with the detector owner. The empty field on every row is a name, and an unnamed row is an unowned row.
Which Row Stays Blank, and What Does a Blank Mean?
A blank owner field is the most informative part of a drawing, because the blank names the interface gap before commissioning finds the gap. Two blanks recur on a three-machine line. The bond between the labeler frame and the detector frame is usually blank, since neither supplier treats the other supplier’s frame as scope. The signal shield on the detector side is usually blank, since the detector supplier terminates inside its own enclosure and the integrator owns the run between machines. In practice a drawing exercise which walks five rows with the plant electrician converts two blanks into two purchase-order lines before the machines arrive, and a retrofit supply and install split is the same conversation on an existing line.
Which Cable Gets Which Shield Rule?
Why Do Two Shield Rules Look Contradictory?
Two rules are quoted on every installation, and the two rules belong to two different cable classes. Rule one: bond the shield at both ends on the drive-to-motor cable. Rule two: bond the shield at one end on every signal cable running parallel to the motor cable. The inversion is the point. The motor cable is the source, and a source needs a return path at both ends to keep current inside the shield. The signal cable is the victim, and a shield bonded at both ends turns a parallel run into an antenna for the current the motor cable is already carrying. Field practice adds a third instruction: keep the two cable classes apart, or divide the classes inside a shared tray with a continuous grounded divider. A single-ended bond on a source cable and a double-ended bond on a victim cable are the two most common site errors.
Where Does the Rule Reach the Drawing?
The rule reaches the drawing as a cable schedule line rather than as a note. Each cable gets four fields: class, source or victim, termination at each end, and gland type at each end. A schedule in that form makes both rules checkable at a glance, because a source class with a single-ended termination is visible as an error. The gland field matters more than the shield field, since a braid folded back over the jacket and held under a cable tie is an unterminated shield in practice. For example, a photograph of each gland taken during the build closes the field, and the photograph belongs in the acceptance pack. A machine supplier’s documentation reaches the machine boundary: PE terminals, the fitted drive filter, the motor cable and the bonding points. The interconnection between machines belongs to the integrator’s drawing, which is why the line safety interface validation is a separate document with a separate signer.
What Makes a Commissioning Run a Record Rather Than a Demonstration?
What Is Counted, Against Which Population?
A commissioning record counts events against a stated population, and a demonstration shows one bottle passing. Four fields make a count usable. First, the population is a stated number of bottles at a stated speed class, and the labeler in our fully automatic class runs 40 to 300 pieces per minute, so speed belongs beside the number. Second, the test pieces are ferrous, non-ferrous and stainless samples, each passed before and after every ramp. Third, the ramp sequence is start, run, stop and restart, repeated a stated number of times. Fourth, the counter is the reject log, with good-bottle rejects and missed detections recorded separately. A run which reports only the good bottles after the fix has no baseline, cannot fail, and proves nothing.
What Does the Acceptance Sentence Say, and What Happens If It Fails?
The acceptance sentence is one paragraph agreed before the run, and the remedy clause sits inside the same paragraph. A workable sentence names the baseline, the ramp count, the population, both counts and the allowance. With the drive stopped the good-bottle reject count is the baseline; with the drive ramping the same count must not exceed the baseline by more than the agreed allowance over the stated population. The remedy clause answers three questions in advance: who reworks the filter, the cable route or the shield termination; whether the line runs on a documented deviation during the rework; and who signs the deviation. In practice the sentence fits on one page signed by the integrator, and the trial labeling run on the buyer’s own bottles with video returned is the labeler-side evidence filed beside the page.
Frequently Asked Questions
Whose Bonding Belongs on the Interface Drawing?
Bonding between two machines belongs on the interface drawing when neither supplier’s scope reaches the other frame, and the bond is one row with one named owner. The labeler’s scope ends at the PE terminal on the labeler frame; the detector’s scope ends at the PE terminal on the detector frame. The connection between the two terminals belongs to the integrator who supplies the line, and an unassigned bond becomes a delay at commissioning.
Which Standard Proves That the Two Machines Can Coexist?
No published immunity standard is written as a commissioning test for a line, and the proof is a counted record against a baseline. According to IEC 61000-6-2, the generic immunity standard applies only if no relevant dedicated product or product-family EMC immunity standard exists, which leaves the line test to the record. The record supplies what a standard cannot: the drive stopped as the baseline, ramps repeated a stated number of times, and both counts stated against the population.
Is a False Reject a Detector Fault or a Labeler Fault?
A false reject is usually neither machine’s fault, and the fault sits on the connection between the two machines. The labeler’s drive ramps current, the disturbance travels on the connection, and the detector reports the disturbance. When the same test piece passes with the drive stopped and fails on the ramp, the detector is healthy and the connection is the subject.
How Many Ramps Make a Commissioning Test Valid?
No fixed ramp count is valid on its own, and validity comes from a count stated against a population before the run. The population is bottles, the trigger is the ramp, and the outcome is a pair of counts: good-bottle rejects and missed detections. In practice ten ramps at a stated speed, with test pieces before and after each ramp, is a workable starting point agreed in writing before the first ramp.