Short answer: a standard labeling machine is a conditional yes for a solvent filling room, and the zone drawing decides. The machine may stand inside the room when the classified volume ends before the first ignition source. The machine may stand inside the volume when every part in the volume carries a recognised type of protection. Zone 0, Zone 1 and Zone 2 describe gas volumes. Zone 20, Zone 21 and Zone 22 describe dust volumes. Both sets describe a space, not a distance from the nozzle. Zone 2 is a place where a flammable atmosphere is unlikely and short lived, according to HSE guidance. Ethanol reaches a flammable range at 3.3% by volume, so a small spill in a still room is enough. In practice, the drawing decides most projects. Three routes follow. Route A keeps the standard machine and moves the zone. Route B purges and pressurizes the cabinet. Route C Ex-rates the head, and the assembly then falls under Directive 2014/34/EU.
Can a Standard Labeler Run Inside a Solvent Filling Room?
A standard labeler is a labeling machine built to the ordinary industrial standard, with no Ex marking on the nameplate and no zone assessment in the technical file. Such a machine may enter a solvent filling room in two cases. The first case is a classified volume that ends before the first ignition source on the machine. The second case is a machine whose parts inside the volume carry a recognised type of protection. Everything else is a refusal or a rebuild. Zone 0 holds an explosive atmosphere continuously, Zone 1 holds an atmosphere occasionally in normal operation, and Zone 2 holds one for a short period only, as set out by HSE in the zone classification guidance. Three routes follow from those definitions. Route A keeps the standard machine and moves the zone. Route B pressurizes and purges the cabinet. Route C Ex-rates the head under Directive 2014/34/EU. The route is chosen from the signed drawing before a purchase order is released.
Step 1: Read the Zone Drawing Before the Machine Datasheet
A zone drawing is a plan that states where a flammable atmosphere may form, which release source created the volume, and how far the volume reaches. Read the release source first. An open filling nozzle, a drum change, a sampling point or a floor drain can each create a volume. Read the ventilation second. A mechanically ventilated room can shrink the volume, and a still room can extend the volume. Read the height third. Vapour from a heavy solvent pools low, while vapour from a light solvent rises to the ceiling. Ask for the signed revision in force, plus the method behind the zones, normally IEC 60079-10-1. The release grade and the ventilation rate set the zone number, according to IEC 60079-10-1, and Zone 0 is reserved for a continuous release. DSEAR places the duty to classify on the employer, and a machine datasheet cannot answer any of those four readings.
Step 2: Fix the Gas Group and the Temperature Class
A gas group is a classification of the vapour by the energy needed to ignite the mixture. Group IIA uses propane as the reference gas, IIB uses ethylene, and IIC covers hydrogen and acetylene. Equipment marked IIB may serve IIA and IIB areas, and never an IIC area. A temperature class is a surface temperature limit, and the scale runs from T1 at 450 °C to T6 at 85 °C. The marked temperature must stay below the autoignition temperature of the solvent. Ethanol carries an autoignition temperature of 363 °C, so a T2 limit of 300 °C is acceptable. A T4 limit of 135 °C, for example, leaves margin for a hot print head. Ethanol also carries a flash point of 13 °C and a flammable range of 3.3% to 19% by volume. A dust layer of 5 mm adds a 75 K margin to the surface limit, according to IEC 60079-14.
Step 3: Put Every Ignition Source on One Parts List
An ignition source list is a drawing overlay that marks every spark, arc and hot surface on the machine. Start with eight families. Conveyor drive motor, stepper motors on the head, variable frequency drive, PLC and HMI, photoelectric and gap sensors, encoder, print head, plus any heated element such as a hot melt tank on a re-commissioned line. Add junction boxes, panel cooling fans and the label web. A 24 V sensor circuit still arcs when a connector is opened. An IP65 rating describes dust and water ingress, not explosion protection. Mark each item inside or outside the volume, then name the protection type for each item inside. Step 1 of the list is the overlay, and Step 2 is the certificate pack. The certificate scope names the group and the temperature class, according to Directive 2014/34/EU. Current builds use SICK and Panasonic sensing with Leadshine steppers, so ask for each sensor certificate.

Route A: Move the Zone and Keep the Standard Machine
Route A is the cheapest route, and the one most often claimed without evidence. Four conditions must hold together. First, the signed zone drawing shows the whole machine outside the classified volume. Second, a wall, an airlock or an extraction booth separates the machine from the release source, and the barrier appears on the same drawing. Third, extraction at the filling head holds vapour below 25% of the lower explosive limit during a drum change. Fourth, the machine draws air away from the zone rather than toward the head. A cooling fan on a standard cabinet can pull vapour into a sparking contactor. In a ventilated room with a small Zone 2 volume, Route A usually holds. Above an open nozzle in Zone 1, Route A does not hold. The zone volume is the test and distance is not the test, according to HSE guidance. In practice, a signed drawing is the only evidence an inspector accepts.
Route B: Pressurize and Purge the Cabinet
Pressurization is a type of protection under IEC 60079-2:2014 in which a protective gas holds the inside of an enclosure above the surrounding pressure. A flammable atmosphere cannot enter the enclosure while the pressure holds. The standard defines three variants: px with continuous monitoring and an alarm, py with monitoring and indication, and pz without an alarm. The certificate states which variant allows which zone reduction. The cycle is fixed. First purge the enclosure, then prove the pressure at the switch, then hold the pressure, and finally trip the power on loss of pressure. The enclosure must be gas tight at the cable glands, the door seals and the cooling path. The air supply must be clean and oil free. One limit decides most projects. Purge covers the enclosure only, never a stepper motor or a print head mounted outside the enclosure, according to IEC 60079-2.
Route C: Ex-Rate the Head and Name the Signatory
Ex-rating is a rebuild in which every part inside the zone is replaced with equipment carrying a recognised type of protection. Flameproof d contains an internal explosion, increased safety e removes sparks and hot surfaces, intrinsic safety ib limits the energy in a circuit, and dust protection t covers a powder room. Each part arrives with a certificate and a marking that includes the group and the temperature class. The assembly then needs a documented assessment, first of the certificates and second of the assembly. A collection of certified parts on one frame is not automatically a certified machine. Category 3 equipment may go to market under internal production control, according to Directive 2014/34/EU. Category 2 needs an EU-type examination certificate from a notified body. Category 1 adds production quality assurance on top. The nameplate must show the Ex marking, the category and the temperature class, and the signature on the declaration of conformity is the point where a rebuild becomes a new machine.
What to Demand in Writing, and the Decision Table
A zone statement is a one page document that names the zone, group and temperature class the machine is built for. The statement names the protection type of each part inside the zone, and the standard behind each claim. Request the statement in writing before the quotation is priced. Three documents travel with the statement. First the Ex parts list, which gives a drawing position for each protected part. Second the certificate set, which covers the exact model of each part. Third the commissioning record, which proves purge flow and earth bonding continuity. A supplier who answers with the phrase ATEX compliant and cannot produce the certificate scope has answered nothing. The scope defines the group, the temperature class and the zone where the part may be used, according to Directive 2014/34/EU. The employer keeps the duty to classify the area, and the supplier keeps the duty to prove the equipment.
Which documents close the file
A closed file is a folder in which every claim on the quotation has a paper behind it. The folder is checked before the machine is unloaded, not after. The zone drawing sits first, signed and dated, with the release source and the volume marked. Next comes the zone statement, then the Ex parts list with a position on the general arrangement drawing. The certificate set follows, copied in full rather than by front page. The schedule on each certificate lists the group, the temperature class and any condition of use. Then the commissioning record: purge flow and pressure, interlock test, earth bonding continuity at each point. The declaration of conformity closes the folder, according to Directive 2014/34/EU. The machine is not accepted while any of the six documents is missing, and the manufacturer guides set the same order for a new build.
Decision table: zone, group and route
| Zone | Group | Route that fits | What must be signed |
|---|---|---|---|
| Zone 0, Zone 20 | Any group | Route C only | Category 1 certificate and declaration |
| Zone 1, Zone 21 | IIA or IIB | Route B for the cabinet, Route C for field parts | Type px certificate plus Ex parts list |
| Zone 1, Zone 21 | IIC | Route C only | Category 2 certificate for each part |
| Zone 2, Zone 22 | IIA, IIB or IIIC | Route A, or a standard machine with Ex ec motors | Zone drawing plus motor certificates |
| Zone 2, Zone 22 | IIC | Route B or Route C | Type pz certificate or Ex parts list |
| Outside the volume | Not applicable | Route A | Signed zone drawing only |
How to run the decision in one meeting
A decision meeting is a single session with three inputs on the table. The inputs are the signed drawing, the solvent data sheet and the parts list, and each one comes from a different desk. Step 1 is the drawing, because the zone number and the volume fix the boundary. Step 2 is the data sheet, because the flash point decides whether a flammable atmosphere is credible at room temperature and the autoignition temperature decides the temperature class. Step 3 is the parts list, read as eight families and marked inside or outside the volume. The route then falls out of the table above, according to the zone and the group. In practice, the PLC and IO list shows which control hardware sits nearest the zone. Close by naming the documents that must arrive with the quotation. HiPaks asks for the zone drawing before an Ex build is quoted, because the group and the temperature class change the parts list.