Your Slab Is 8 mm Low: Which Floor Number Do You Sign?

A floor number is a measurement with an owner, and the slab carries five of them. A footprint deviation is shape between bearing points. A slope is a rate along a run. A floor classification is a statistical profile of a trafficked surface. A pad elevation is a setting-out value against a site datum. A deflection is the movement of a support point under load. According to ASTM E1155-20, the F-number method measures floor surface profiles to obtain characteristic FF flatness and FL levelness numbers. Each measurement carries a different instrument, issuer and document, and mixing the five is how a purchasing director signs a figure nobody can enforce.

Five Floor Numbers, One Signature: Which One Goes in the Contract?

What Does Each of the Five Floor Quantities Measure?

A footprint deviation is the shape between the points where the base bears, across the covered area. A slope is a rate, read along a run with a level at two ends. A floor classification is a statistical profile of a slab, sampled at random points against the slab’s own project specification. A pad elevation is a setting-out value against a site datum. A deflection is the movement of a support point once machine and product stand on the pad. First, only deviation and deflection describe the interface the machine feels. Second, slope and classification are the builder’s. Third, pad elevation bridges two trades: 1) the datum, 2) the finished level, 3) the base plate. For example, a passing classification on a tiled slab says nothing about the shape under one foot.

Which Floor Number Can Each Party Actually Issue?

A floor number is evidence only when the issuer can be named, because the signature follows the instrument. According to IFTI, slab, housekeeping pad and machine base are three levels with three tolerances. The table sorts the five by what each reading proves, who can sign, and what the number cannot support.

Quantity What it proves Who can issue it What it cannot prove
Footprint deviation shape between bearing points installer, against the OEM drawing that the base stays straight under load
Slope along a run rate of fall between two ends surveyor, with level and datum that the whole footprint is flat
FF/FL classification that a sampled slab met its spec independent floor tester that the machine pad meets OEM tolerance
Pad elevation that the pad landed where drawn site engineer, pre-install that concrete under an anchor is sound
Deflection under load that a support point moves when loaded machine builder, buyer’s weights that the movement repeats after a week
A single-side labeling machine bolted to a conveyor frame on a plant floor, the arrangement where the labeler base and the conveyor legs share one slab

Is Flat the Same as Level, and Is a Floor Classification Either?

What Does a Floor Flatness Test Measure?

A floor flatness test measures a surface profile by random sampling, and the sampling is the part buyers miss. According to ASTM E1155-20, the F-number method gives a quantitative measurement of floor surface profiles to estimate characteristic FF flatness and FL levelness numbers. The same scope notes warn that results shall not be used to enforce contract flatness and levelness tolerances on floors intended to support fixed-path vehicle systems. Two properties follow. First, the sample is drawn across the trafficked area, not over one machine base. Second, a level line along a run is a slope test, and a slope test cannot produce an F-number. In practice, the F-number answers 1) whether the slab met its specification, 2) whether the test areas were random, 3) nothing about the machine pad.

Where Does the Binding Machine-Base Number Come From?

The binding machine-base number comes from the builder’s installation drawing, not from the slab’s project specification. According to IFTI, the slab, the pedestal or housekeeping pad and the machine base sit at three levels, and the installation manual is the only document which is the final word for a specific unit. As of 2026 the guide adds that a passing score for the surrounding slab says nothing about whether the local machine pad meets the OEM tolerance, and that the two approaches are not interchangeable. First, the floor tester closes the slab specification. Second, the site engineer closes the pad elevation. Third, the machine builder closes the base. In practice, the builder’s drawing is the only figure an acceptance test can hold.

The Low Corner: Which Correction, and Does the Tile Stay?

Which Three Corrections Fit a Low Corner?

Three corrections fit a low corner, and each one changes a different drawing. The first keeps the tile and takes up the fall inside the machine’s own leveling system, so the base is set to the machine rather than the machine to the slab. The second builds a soleplate or a grout bed under the base, which turns a site condition into a machine-mounted part with a drawing. The third cuts the tile out of the footprint and repairs the concrete, which resets the pad elevation and adds edges and a cure. The rank comes from two facts, not from a vote: 1) whether the tile layer is bonded, 2) whether the low point sits inside the leveling range. The route in is a separate survey, covered in the sectioned shipment route survey.

What Test Decides Whether the Tile Stays?

The tile question is a decision with a test, not a vote among fitters. The test is a bond check at every support point: lift a core or cut a test patch, then read 1) whether the tile layer is bonded, 2) whether the bed is continuous under the bearing area, 3) whether the glaze carries load. A layer bonded at three points and hollow at the fourth is a finish, and the fourth carries the corner. First, a failed bond check at any support point ends the keep-the-tile branch. Second, a low point outside the leveling range ends the same branch even with a sound bond. Third, the flooring contractor or the surveyor signs, with the builder accepting the correction. In practice, a show of hands fails two years later.

What Gets Grouted, What Gets Anchored, and What Stays Free?

What Does Grout Do That a Shim Cannot?

Grout carries bearing over the whole designed area, and a shim stack carries bearing at a point. A non-shrink machinery grout fills the space between base and support so load spreads across the plate, while loose shims leave it empty. Four rules follow. First, every foot must bear, with no rocking feet, no stacked washers and no point contact. Second, nothing gets grouted which has to move later: 1) guards, 2) removable panels, 3) adjustable feet and conveyor legs. Third, the anchor is not the bearing. Fourth, a washdown floor carries its own falls, and the drain detail in the washdown IP and drain slope guide stays separate from the pad. In practice, a corner pulled down by an anchor is the defect a survey finds in week two.

What Do the Anchors Hold, and What Must Stay Free?

Anchors clamp the machine to the concrete, and clamping is the whole duty. An anchor must never pull a low corner down, because the tension goes into the base frame and reappears as a twist at the label station. The sequence is the clause. First, the grout goes in and reaches the strength named on the grout manufacturer’s data sheet. Second, the anchors are tightened to the figure in the installation drawing. Third, production starts: 1) the grout carries load, 2) the anchors hold, 3) the first week proves both. Anchors belong in sound concrete only, and tile over a slab is not sound concrete. Our placement figures are up to plus or minus 0.5 mm on the semi-automatic class and up to plus or minus 0.2 mm on the MT-807, all excluding product and label variation.

What Makes a First-Week Re-Check Survive an Argument?

What Four Conditions Make a Re-Check Comparable?

A re-check is comparable only when four conditions match the baseline, and a reading without position, instrument and state cannot be compared with the next one. First, the instrument class: the same level or the same laser, or the two readings are two different tests. Second, the load state, because an empty machine and a loaded machine press the supports differently, so the record names 1) the state measured, 2) the product used, 3) the fill level. Third, the temperature at the time of reading. Fourth, the grid points and the datum, marked on the floor and numbered on the sheet. Add the owner, because in practice the installer’s technician has left site before the week ends. According to CNC Media, an installation level record is an input to the acceptance programme, not a performance guarantee.

Where Do the Survey and the Re-Check Attach?

The survey and the re-check attach to two documents, and the attachment is the reason to pay for either. The pre-installation survey attaches to the acceptance certificate as its floor annex, dated before the machine lands, carrying 1) the instrument, 2) the load state, 3) the signature. The first-week re-check attaches to the same certificate and to the warranty file as the baseline record. According to IFTI, many equipment OEMs specify foundation flatness and levelness as a condition of the installation warranty, so a documented out-of-tolerance foundation can be grounds for denying a claim, regardless of whether the foundation was the actual cause. In practice, that file is the buyer’s answer, and the warranty claim evidence guide is where it gets used. The build window is costed in the offline pre-build downtime plan. Send the survey sheet with the bottle drawing before a quote, and ask for a trial on your own bottles with the video returned: contact form.

Who Signs the Floor Acceptance, the Buyer or the Installer?

The buyer signs, and the installer countersigns the figures. A floor acceptance is a buyer’s document because the buyer owns the consequence: a machine which will not hold registration on a moving base is a production loss, not a defect. Three signatures make the record usable: 1) the surveyor signs the slab and pad, 2) the builder signs the base against the installation drawing, 3) the buyer’s engineer signs the acceptance. According to IFTI, the installation manual is the final word for a specific unit, so the builder’s figure outranks every site measurement on the sheet.

Can the Machine Be Accepted Before the Floor Is Signed Off?

No, and the week between installation and acceptance is the part most often left out. A machine can be commissioned on an unsigned floor, and the risk lands on the buyer. Two rules close the gap. First, the machine’s own acceptance run happens on the floor record, so the annex is dated before the first bottle rather than after the first complaint. Second, the week of production is the acceptance point, which is why the re-check is a clause and not a courtesy visit. In practice, the wording which works is short: the machine is not accepted until the frame stays within the agreed figures after one week of running.

Does a Low Corner Void a Labeling Machine Warranty?

A low corner does not void a warranty by itself, and no supplier should be asked to say otherwise in a quotation. What a floor condition changes is the evidence available when a bearing or a drive fails: a documented out-of-tolerance foundation gives a builder a ground to question a claim, and a documented in-tolerance foundation closes that argument. Two records decide the conversation: 1) the pre-installation survey with its instrument, load state and signature, 2) the first-week re-check, taken the same way. According to IFTI, many OEMs make foundation flatness a condition of the installation warranty, which is a reason to keep the file, not to fear the floor.

Get a factory quote for your own container.

Send the container, label size and target speed. You get a short list of machine options, an indicative price and a free test-run plan on your own labels.

Get a Factory Quote Request a Free Test-Run Video

Share

Related reading

Keep reading.

More guides from the same category, chosen for the machine types and container details they cover.

Labeling Machine Manufacturer Guides

Die-Cut Gap or Eye Mark: Whose Drift Is It?

Registration drift on a pressure-sensitive labeler reaches a distributor as an argument rather than as a fault, and the argument returns with every batch because three parties measure three different things. A die-cut gap and an eye mark are converter geometry. Registration is a machine reading of that geometry at line speed. Once the numbers ... <a title="Die-Cut Gap or Eye Mark: Whose Drift Is It?" class="read-more" href="https://hipaks.com/die-cut-gap-eye-mark-drift-order-lines/" aria-label="Read more about Die-Cut Gap or Eye Mark: Whose Drift Is It?">Read more</a>

Nov 26, 2026 · 11 min read
Read guide
Labeling Machine Manufacturer Guides

How Many Bottles Prove a Labeler? The Sampling Plan

An acceptance sampling plan for a labeler is a rule for deciding, from a counted sample of labelled bottles, whether the machine may be accepted, and the bottle count is the last item to fix rather than the first. Five parts carry the plan: the population, one bottle lot crossed with one label station and ... <a title="How Many Bottles Prove a Labeler? The Sampling Plan" class="read-more" href="https://hipaks.com/labeled-output-acceptance-sampling-defect-classes/" aria-label="Read more about How Many Bottles Prove a Labeler? The Sampling Plan">Read more</a>

Nov 25, 2026 · 11 min read
Read guide
Labeling Machine Manufacturer Guides

Uptime Clause: Which Stops Count Against the Supplier?

An uptime clause is a formula with four decisions written into the purchase contract, and month one is where those decisions meet an installed machine. The four decisions are the two clocks, the closed list of exclusions, the boundary between supplier stops and buyer stops, and the evidence attached to every stop. On a pressure-sensitive ... <a title="Uptime Clause: Which Stops Count Against the Supplier?" class="read-more" href="https://hipaks.com/labeler-uptime-clause-first-month-stoppage-ledger/" aria-label="Read more about Uptime Clause: Which Stops Count Against the Supplier?">Read more</a>

Nov 24, 2026 · 11 min read
Read guide