A labeling machine ships in sections through a 1.4 m service door and a 1 t goods lift on one condition: the split is a design decision made before the crate drawing is approved, not a choice taken on the delivery day. A pressure-sensitive labeler opens at five places: base frame, applicator head, conveyor sections, control cabinet and guarding. Four of the five tolerate a millimetre of movement when the seam closes. The head-to-conveyor seam does not, and the route survey exists to prove that seam can be reopened and returned to datum inside the room.
One point that a generic rigging checklist leaves out: the room must also hold the sections plus the floor area needed to align them.
Can a Labeling Machine Be Shipped in Sections Without Losing Its Alignment?
Which Seams Open, and Which One Must Not Move?
A split point is a joint the builder designed to open for transport and close again on site, and alignment survives the trip only where every seam has a datum to return to. A pressure-sensitive labeler splits at five places: base frame, applicator head, conveyor sections, control cabinet and guarding. Four of those places tolerate a millimetre of movement. The fifth does not. The seam carrying the applicator head onto the conveyor, with the guide rail or star wheel that fixes bottle position, decides where the label lands. An error at that joint repeats on every bottle.
Ask two questions before the crate drawing is approved. First, is the head-to-conveyor joint dowelled, pinned or shimmed? Second, what written procedure returns the head to datum? A split with no answer to the second question becomes a re-commissioning job on delivery day.

Why Is the Assembly Envelope Larger Than the Installed Footprint?
The assembly envelope is the floor area needed to land sections, stand them, align seams and couple frames, and that envelope is always larger than the installed footprint. Three reasons drive the gap. Sections arrive on skids and are set down at an angle before lifting gear reaches the lifting points. The head needs room on both sides while the seam is closed. The final position stays empty until the frames are coupled, so sections stand on staging floor at the same time.
For example, a machine ending against a wall may still need clear floor behind the head on the day. Mark the footprint and the envelope on the floor before the crate ships, then walk the marked outline past drains, columns, traffic lanes and door swings. A conflict found on that walk costs a drawing revision. The same conflict found on delivery day costs a crane or a second route.
Fault 1: The Section Clears the Door and Jams at the Turn
A clear opening is the tape measurement between the finished faces of a door frame at the tightest point, and a nominal 1.4 m door rarely passes a 1.4 m load. The 1.4 m on a drawing is often the structural opening. Architraves, a door leaf standing at 90 degrees, hinges, a closer arm, a threshold plate and a step each take width or height, and the tightest point governs the whole route rather than the widest doorway on the way.
Turning space usually fails before width does. A section on a skid pivots about a corner, so the swept path at a right angle needs floor outside that corner which a straight corridor never showed. Work through four measurements in order. First, the clear opening of every doorway at three heights. Second, the headroom under pipes and cable tray, the threshold height and any ramp. Third, the clear width at each turn and the swept path at full section size. Finally, the largest packed piece set out at full scale and walked along the route.
Fault 2: The Lift Is Rated One Tonne and the Handling Load Is Not the Section Weight
A goods-lift rating is a maximum allowable load, not a target, and the figure that has to clear it is the gross handling load rather than a section weight. Three numbers settle the lift, and all three belong on one line of the survey sheet.
First, the gross handling load: section mass plus crate or skid plus slings, spreader beam or pallet truck, plus the 2 people in the car if anyone is allowed to ride. Second, the contact area under that load, because a compact section standing on four small feet or on steel skates can exceed a lift floor point-load allowance while the total stays under one tonne. Third, the crated height against the lift door clear height, which differs from the car internal height and differs again from the car depth.
The loading and unloading checklist is set by HSE, and according to HSE, lifting equipment must carry a marked safe working load and the lifting operation must be planned by a competent person and supervised. A one tonne plate on a lift door is a label, not a plan.
Fault 3: The Floor Passes on Total Weight and Fails Under a Foot or a Skate
A floor check turns on two different numbers, and the uniformly distributed load is the easier of the two. A labeler is light against a filler or a capper, so the slab usually passes on total mass. The point load under a foot, a levelling pad or a steel skate is where a suspended slab, a trench cover, a drain gully or a cellar ceiling fails.
The route floor needs the same check as the final position. Rigging skates and toe jacks concentrate load into a small contact patch while the machine moves, and a pallet truck on a ramp adds a horizontal force that the resting machine never applies. A slab which carries the machine in place can still fail under a skate at a corner.
Ask for the machine mass and the foot layout, hand both to a structural engineer, and require a written assessment covering the route, the staging area and the final position. An assessment naming the final plinth alone answers a third of the question.
Fault 4: It Fits, It Is Reassembled, and Placement No Longer Holds
Reassembly is the point where a delivery becomes a machine, and the only proof that a seam came back correctly is a placement run on the buyer’s own bottle at the contracted rate. A designed split returns to a datum by dowel, pin or shim under a written procedure. The run that proves the return is the first-off test used at the factory acceptance test, read against the accuracy band quoted for the machine class.
HiPaks runs the customer’s own bottles before shipment and sends the video back, according to HiPaks commissioning practice, so a re-proof on site repeats a known result instead of inventing one. The frozen bands are plus or minus 0.5 mm on semi-automatic machines, plus or minus 1 mm on automatic machines and up to plus or minus 0.2 mm on the MT-807, with product and label variation excluded. Use the buyer’s bottles, the buyer’s label lot and the contracted rate, then write a first article record with the spread and the direction. A seam holding inside the band on 3 consecutive bottles is closed. A seam proved on one bottle is not proved at all.
The Route Survey Sheet: What Is Measured, with What, and Who Countersigns
What Goes on the Survey Sheet?
A route survey sheet is one revision-controlled page carrying a measurement, an instrument and a signature for each gate. Six gates cover a labeling machine move, and each row below settles a fault before the crate is built.
| Gate | What is measured | Instrument or record | Who countersigns |
|---|---|---|---|
| Door and turn | Clear opening at the tightest point, then the swept path at the tightest turn | Steel tape at three heights, then a floor template at full size | Site engineer and rigger |
| Goods lift | Gross handling load, contact area under the load, crated height against door clear height | Lift plate reading, crate drawing, sling and skate list | Lift manager and supplier |
| Floor, route and position | Distributed load and point load at the final position, at each turn and along the skate path | Structural engineer assessment and machine layout drawing | Structural engineer |
| Room | Installed footprint and assembly envelope marked on the floor | Chalk line walked past drains, columns and door swings | Installer and plant engineer |
| Seam | Head-to-conveyor datum recorded before the split is opened | Reassembly procedure and datum record | Builder technician |
| Release | First-off run on buyer bottles at the contracted rate | First article record with spread, direction and label lot | Quality and builder technician |
Who Countersigns the Sheet, and What Happens When the Site Changes?
A countersignature is a named person accepting one number, not a department accepting a project. Four signatures carry the sheet: the site engineer owns the route and the floor, the rigger owns the lift and the assembly envelope, the lift manager owns the rating, and a structural engineer owns the slab wherever the route crosses a suspended floor or a cellar. The builder’s technician signs the seam procedure, because the datum is the builder’s design.
Two rules keep the sheet alive. First, the sheet is an annex to the purchase order, so delivery depends on a signed revision rather than a verbal walk round. Second, a site change forces a new revision and a fresh signature, not a change order argued in the doorway with a section on a skid.
A countersignature also records a legal duty, since according to LOLER 1998 a lifting operation must be planned by a competent person and supervised, and lifting equipment needs thorough examination.
What Has to Be True Before the Purchase Order Is Signed?
A purchase order clause is a risk transfer, and five clauses carry the move-in risk. 1. The split drawing carries, per piece, the packed length, width and height, the gross weight, the centre of gravity, the lifting points and the handling order. 2. The survey sheet is signed at its current revision and annexed. 3. The lift plan names a competent person. 4. The reassembly procedure names the datum, the technician and the first-off run on the buyer’s bottles at the contracted rate. 5. The builder states in writing whether the split sits inside the CE or UKCA technical file or the hygiene validation, and who re-issues it under Regulation (EU) 2023/1230.
Lead time on an automatic labeling machine runs 7 to 25 days by configuration, and no part of that window absorbs an unsigned survey. For example, a survey signed after the crate is built can only change the route, not the split. Crate contents and the install calendar are in the nine items beyond customs paperwork and the offline pre-build.
Frequently Asked Questions
Can a Labeling Machine Go Through a 1.4 m Door in One Piece?
A one-piece move is possible only where the clear opening, the handling gear and the turning space all clear the largest packed piece, and a tape rarely agrees with the drawing. A single piece needs the measured opening plus clearance for slings, skates or a pallet truck, so a 1.4 m opening usually settles the question.
Is a One Tonne Goods Lift Enough?
The rating is a ceiling, not a target. The load is section plus crate plus gear plus anyone riding, with the contact area and crated height checked against the car and the lift door. Put the three numbers on the survey sheet and let the lift manager sign the one that governs.
Which Joint Decides Whether the Machine Still Labels Correctly?
The head-to-conveyor seam decides label position, with the guide rail or star wheel that fixes bottle position. Placement is measured against bottle position, so movement at that seam repeats on every bottle. The other four split points tolerate adjustment.
What Has to Be Re-Proved After Reassembly?
Placement is the proof, on the buyer’s bottles, at the contracted rate, against the accuracy band quoted for the machine class. A designed split with a datum procedure and a first article record turns that run into a release, and no datum turns the same run into an argument.